Masterplan
4. Cost
AACE Class 4 (−30% / +50%). Capex excludes GPUs. Sensitivity is in §4.4.
4.1Capital estimate, class, and the range we may claim
Standard AACE 18R-97. Class 4 is entitled to -30% / +50%. We do not claim tighter.
Rental-gen (halls, no owned turbines) P50: 5,360.5 $MEstimate, range $3,752M to $8,041M. Owned-campus P50: 6,738.1 $MEstimate. Per MW IT: $15.3M rental / $19.3M owned. Owned-campus P50 is the compiled total (halls, MEP, site, and generation). Atlas site-infrastructure bands are a separate line.
| Atlas program | Load | Quoted capex |
|---|---|---|
| Phase 0: Diligence Months 0–9 | No load yet. Licensed microwave link live by ~month 3 for site connectivity. | $2–5M: study program $1.6–3.7M plus route diligence and microwave. |
| Phase 1: First power Months 6–24. Target first fire ~month 12–15. | 150–200 MW of generation (~100–133 MW of computing load), with an 85 MW battery system. | $160–280M site infrastructure (gas lateral $45–70M, batteries $38–59M, civil and camp $65–115M, water $9–17M, fiber $12–19M). Generation is rented, not bought (see below). |
| Phase 2: Scale Months 24–48 | Toward 500 MW: rented turbines convert to owned equipment, engine halls add efficient baseload. | $400–600M this phase (generation ownership conversion, engine halls, gas expansion, second pad). |
| Phase 3: Grid connection 2030 and later, when the state reopens the queue | The 345 kV cut-in of the 350 MW campus. On-site fleet becomes backup and peak sales. | $45–80M for the switchyard and line connection, plus state-required deposits (~$100k per MW under the proposed rule). |
| Phase 4: Toward 3 GW After the 345 kV cut-in, later tranches | Toward 3,000 MW IT on the Cottonwood corridor. Grid-hybrid. Not Palo Duro fuel. | Not compiled. Optionality on later tranches of the same ranch. |
Atlas halls are quoted at $9–12M per gross MW in the plan popups, which is the same neighborhood as the compiled Class 4 vertical of $10.23M per MW IT. Owned aero is Atlas $1,400–1,900/kW; this study uses $1650/kW.
4.2Cost breakdown
| WBS | $M | Band | Kind |
|---|---|---|---|
| Campus halls + MEP Includes halls, MV/LV distribution, dry/hybrid heat rejection. Excludes generation, lateral, fiber, camp, GPUs. | 3580.5 | 2685.4–4833.7 | Estimate |
| Civil, pad, camp, roads | 180 | 120–250 | Plan |
| Water, RO, tanks | 22 | 12–35 | Plan |
| Gas lateral | 128 | 90–165 | Plan |
| BESS | 60 | 42–81 | Estimate |
| Fiber both legs | 18 | 12–22 | Plan |
| Electrical equipment (inside halls, not additive) Per-section N+1; campus-wide 5000 A busway takeoff is not used. | 125.2 | n/a | Calculated |
| Owned aero-equivalent block (campus) | 1025 | 871–1179 | Estimate |
| Rental generation capex (first power) | 0 | n/a | Plan |
| Direct (rental case) | 3988.5 | ||
| Soft costs 12% | 478.6 | ||
| Contingency 20% | 893.4 | ||
| Total rental (halls, gen rented) | 5360.5 | ||
| Total owned campus (headline) | 6738.1 |
Electrical equipment check (125.2 $M) sits inside campus halls. Per-section N+1 killed the campus-wide 5000 A busway takeoff. Do not add the equipment check twice. Capex excludes GPUs: true.
4.3Unit economics
- $15.3M per MW IT built (rental case, GPUs out).
- Fuel $24.71/MWh at the campus boundary. Heat rate 9,150 Btu/kWh (9.15 MMBtu/MWh).
- Annual fuel ~$77.8M at CF 0.7, on 3,147,424 MWh and 28,799,036 MMBtu.
- Gas burn 78.9 MMcf/d. Palo Duro’s certificated 80,000 Dth/d is roughly 29.6 MMcf/d, which is the first-power tranche and not this.
- Capex spread over 15 years at that CF: roughly $209/MWh-IT owned (rental halls-only $167). A finance sketch, not LCOE.
- CUE 0.586 kgCO2/kWh-IT · 1,528,071 tCO2/yr at CF 0.7, which is 20.4× the 75,000 tpy PSD greenhouse-gas trigger. Title V and PSD/GHG BACT are required. EPA NG EF, no methane leakage.
- Efficiency-driven operating cost is the fuel line plus dry-plant water (small) plus people. SG&A is not included.
Fuel only, not all-in LCOE. Heat rate 9.6 MMBtu/MWh on Waha $2.10 plus an assumed $0.60 of transport, with the Palo Duro tariff still unfiled. Annual $M scales with compiled facility MW at 70% CF. Campus opex (people, water RO, maintenance) is not in this number. Capex $/MWh-IT is P50 owned-campus spread over 15 years at 70% CF, which is a finance sketch rather than LCOE. The full case with debt service and coverage is in the finance block.
4.4Sensitivities
One lever at a time on the owned-campus total, loaded with soft cost and contingency. Campus dollars per megawatt is the wide bar. Owning versus renting generation is binary. The laterals are small in dollars and large in schedule.
| Lever | Down | Up | Δ $M |
|---|---|---|---|
| Campus $/MW IT ±20% Estimate Finite difference on the Class-4 campus line, loaded with soft+contingency. Not autodiff. | 5775.7 | 7700.5 | 716.1 |
| Rent generation instead of owning Selected Binary. Campus headline is owned aero-equivalent. Rental is the first-power bridge. | 5360.5 | 6738.1 | 1377.6 |
| Rural factor 0.62–0.85 vs 0.72 Estimate How much West Texas actually discounts Silicon Valley. | 6161.4 | 7487.9 | 749.8 |
| Contingency 15–30% vs 20% Selected | 6457.4 | 7299.6 | 561.5 |
| Gas laterals $90–165M vs $128M Plan | 6687 | 6787.8 | 38 |
| BESS ±30% Estimate | 6713.9 | 6762.3 | 18 |
| Fiber both legs vs one Plan A single lateral reads as Tier-2-only to tenants. | 6726 | 6738.1 | 9 |
4.5Contingency
AACE 44R-08 risk-based placeholder. Class 4 typical 15–30%. 20% used until the risk register is Monte-Carlo'd on the WBS.
20% on (direct + soft) = 893.4 $M. Class 4 typical 15–30% is itself a tornado lever. AACE 44R-08 would replace this placeholder with a risk-register Monte Carlo on the WBS once quotes exist.
4.6Returns
Coverage is 0.78 against a 1.35 covenant. The case does not finance itself at 165 $/kW-month on this capex.
Yield on cost is 4.96% against debt at 7.80%. Every borrowed dollar dilutes the equity return, so more leverage makes this worse rather than better. The problem is the cost basis and the price, not the capital structure.
Revenue is a single contracted tenant at $165/kW-month with a 90% take-or-pay floor over 15 years. Against $6,738M of capital at $19.25M per MW IT, that is $4,043M of debt at 7.8% over 18 years and $2,695M of equity. Debt service is $425M a year, which EBITDA does not cover.
| Line | $M / yr |
|---|---|
| Fuel, at plant heat rate | 77.8 |
| Generation O&M | 23.6 |
| Facility O&M | 80.9 |
| Insurance | 37.1 |
| Property tax, abated | 28.3 |
| Staffing | 29.7 |
| G&A | 12.5 |
| Total | 289.8 |
Property tax runs at 28.3 $M abated against 80.9 $M unabated. Nobody has asked King County for the abatement, and coverage falls to 0.66 without it. It is the largest uncontracted line in the model. Pending
What has to be true
Breakeven is $229.9/kW-month against the $165 assumed, a 39% gap. Each lever below closes it on its own.
| Lever | From | To | Move | Read |
|---|---|---|---|---|
| Contract price | 165 $/kW-month | 230 $/kW-month | +39% | Above current liquid-cooled comps. Would need scarcity pricing on firm power, which a queue-constrained ERCOT does supply. |
| Capex | $19.3M/MW | $12.8M/MW | -33% | The halls line is a per-MW market index with no scale curve. A campus of identical halls should buy better than the index, and the 20% Class 4 contingency retires with design. |
| Both, split evenly | $19.3M/MW at 165 $/kW-month | $16.0M/MW at 197 $/kW-month | half of each | The realistic path. Neither lever has to move the whole way. |
Coverage against price and capital cost
| $/kW-mo | Capex −15% | Base | Capex +20% |
|---|---|---|---|
| 135 | 4.3% / 0.68 | 3.3% / 0.52 | 2.4% / 0.38 |
| 150 | 5.2% / 0.83 | 4.1% / 0.65 | 3.1% / 0.49 |
| 165 | 6.2% / 0.98 | 5.0% / 0.78 | 3.8% / 0.60 |
| 180 | 7.2% / 1.14 | 5.8% / 0.92 | 4.5% / 0.71 |
| 195 | 8.2% / 1.29 | 6.6% / 1.05 | 5.1% / 0.81 |
Scale economics across the phases
| Phase | MW IT | Capex | $M/MW | If linear | Exponent | DSCR | Breakeven |
|---|---|---|---|---|---|---|---|
| P1 First power, rented generation | 100 | $1,761M | 17.61 | $1,580M | 0.913 | 0.62 | $242 |
| P2 Atlas Phase 2 campus, owned conversion | 350 | $6,906M | 19.73 | $6,906M | 1 | 0.76 | $234.8 |
| P3 Grid connection; campus already live | 350 | $6,906M | 19.73 | $6,906M | 1 | 0.76 | $234.8 |
Returns are calculated from this Class 4 capex and the contract price in the model. They are not fitted to a target IRR.
Open items
- Tenant term sheet: price, term, take-or-pay floor, escalator, credit Pending
- King County and Guthrie ISD abatement posture before FID Pending
- Firm gas price beyond the Waha strip, and who carries basis risk Pending
- Whether GPUs are tenant capital; the case above assumes they are Pending
4.7Incentives, districts, and plats
Separate plats for campus, generation, and any later solar/BESS so each asset can be financed and incentivized apart; infrastructure by cross-access easements. A solar/BESS plat would not qualify for JETI; the gas plant and campus may.
- TIRZ (Tax Code Ch. 311)
- Municipal Management District (LGC Ch. 375)
- County Ch. 381 economic-development agreements
- JETI Act (HB 5 / Gov't Code Ch. 403 Subch. T) covers dispatchable generation, manufacturing, critical infrastructure. Renewable generation and storage excluded.
- Data-center sales-tax exemption (§151.359)
- Freeport exemption
SB6 / proposed PUCT 25.194 security (~$50k/MW posted + $50k/MW non-refundable) applies to a grid path. This campus does not file until Phase 3. A 350 MW filing is on the order of $35M at risk.
Commissioning, commercial, sustainability
- ASHRAE Guideline 0 / Standard 202. not started. Owner's project requirements and basis of design are this report's job to start, not to finish.
- Data-center Levels 1–5 + integrated systems test. EPC. Factory, receipt, installation, functional, integrated. After halls exist.
- QA/QC ISO 9001. EPC. Procurement of the builder, not this solve.
- HSE OSHA 1926 / NFPA 70E. EPC. Arc-flash PPE category in this design is a draft input.
- Handover COBie / as-builts / manifest as twin. later. run_id is the seed of that twin. IFC not emitted in this design.
- Form of contract. EJCDC / ConsensusDocs / FIDIC Silver, owner's choice Pending
- Liquidated damages. Not set. TTP P50/P90 are a model, not a contract date. Pending
- Contractual PUE / WUE. Do not write until TMY + wells + rack schedule exist. Selected
- Warranties / bonding. EPC and OEM. Not this Class 4. Pending
- GPU capex. Excluded from the stack on purpose. Selected
- PUE. computed in this design from cooling mix Design PUE only until commissioned.
- WUE. assumed dry mid-band Illegal to evaporative against MAG 49.
- CUE. sketch from heat rate × EPA NG EF; no methane leakage, no Scope 3 24/7 CFE accounting is a later plat (solar is JETI-excluded).
- LEED BD+C. not pursued in this design Owner election.