Masterplan

5. Schedule

First 100 MW in the low twenties of months. The full campus follows the long-lead order, not the interconnection queue.

5.1Integrated schedule

Months from option day. Solid bars are the first-power critical path: title, air, gas, halls. Outline bars can slip. The grid lane is a parallel path.

Grid (Phase 3, parallel)CommissioningFiber​​​​Electrical​​​​​​Civil & halls​​​​​​​​Gas & generation​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Water​​​​​​​​​​​​​​Environment & air​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Land & title​​​​​​​​​​​​​​​​​​​​​010203040Surface use agreementsSurface u…Plats (campus / gen split)Plats (campu…IPaC + biologist walkWetlands AJD / 404 pathWetlands AJ…Cultural / THCCultural / TH…TCEQ NSR (campus fleet)TCEQ NSR (campus fleet)GCD pre-app + permitGCD pre-app…Fire tanks + RO (dry plant)Fire tanks + RO (dry pla…Owned aero (order → install)Owned aero (order → install)BESS GFMBESS GFMMV / LV install (sections 2–4)MV / LV install (sections 2–4)IRUs Childress + LubbockIRUs Childre…Childress lateralChildress lateralLubbock lateral (diverse)Lubbock lateral (diverse)WETT screening (NDA)WETT screening (NDA)Large-load file (when queue reopens)Large-load file (when queue r…345 kV cut-in345 kV cut-inOption + site accessALTA + minerals runsheetALTA +…Phase I ESA + boringsPha…2D H&H (no FEMA map)2D H&H (no F…TCEQ standard permit (first fire)TCEQ sta…Test wells + 72-hr pumpsTest…Palo Duro capacity askPalo D…Lateral FID + T-49.5 mi first lateral9.5 mi first lateralRental aero on padSecond feed + compressionSecond feed + compress…Pad, camp, roadsPad, camp, roadsHalls, first 100 MWHalls, first 100 MWHalls, remaining sectionsHalls, remaining sectionsPadmount + PCU PO (40 wk)Padmount + PCU PO (…MV / LV install (section 1)MV / LV install (s…Cx first 100 MW (L1–L5 + IST)Cx first…Cx campus remainderCx campus r…Months from option dayCan slipCritical path
Figure 5.1. Integrated schedule.

Staged energization:

GateP50, monthsIT MWWhat
Option day00Studies, capacity ask, IRUs
First fire17.20Rental aero on pad
First 100 MW IT23.51006 turbines, section 1 halls live
350 MW IT campus45.4350All 3 sections live, 16 turbines
First utility MW (if filed)43n/aPhase 3 parallel path, not the campus driver
PhaseActivityStartDurationOwnerNote
P0Option + study access09OwnerAir permit + gas agreement vest tranche 1
P0Water test wells + 72-hr pumps03HydrogeologistFirst study to start
P0Geotech + karst geophysics03GeotechFoundations, C26
P0Phase I ESA, H&H, cultural, AJD06ConsultantsBankable constraint matrix
P0Mineral runsheet + SUAs03Landman / counselPre-LOI
P0TCEQ standard-permit application33–6Air consultantAbilene-class weeks-to-months
P0Palo Duro capacity ask0ongoingOwner / midstreamGates lateral FID
P1Gas lateral 9.5 mi66–9Midstream EPCPipe ~2 mo delivery; no claimed RRC pre-construction delay
P1Rental aero bridge91–2Solaris / ProEnergy / VoltaGrid classWeeks, not years
P1Owned 6× LM2500XPRESS block (first power)order in P0/P112–24+OEM / packagerIf not renting first fire
P1BESS first-power 56 MW / 25 MWh96–12IntegratorGFM, NFPA 855; campus is 280/125
P1Pad, halls, MV yard (first section)612–18National DC builderPrefab halls; power is critical path
P1Fiber laterals (both)612–24Carrier / FiberLight / ZayoROW + build
P1First 100 MW IT live15n/an/aA tranche. Model P50 ~21 mo; revert if not by month 30
P2Second gas lateral + compression + recip hallsfirst fire12–24Midstream / OEMPalo Duro does not fuel 350 MW IT
P2TCEQ case-by-case NSR (campus fleet)early P16–12Air consultant724 MW >> 360 MW standard-permit ceiling
P2350 MW IT campus live24n/an/a3 116.667 MW sections; model P50 in the JSON
P3ERCOT large-load filingqueue reopen12–18 studyWETT / ERCOTP50 energization ~2030

5.2Critical path

  • TCEQ standard permit (first power) and NSR (campus fleet). Nothing fires without the standard permit. 724 MW campus is above the ~360 MW ceiling, so NSR is on the P2 path. Plan
  • Palo Duro agreement + 9.5 mi lateral, then the P2 second feed. The fuel path is the long pole on BTM. Palo Duro does not fuel 350 MW IT. Uncommitted capacity is still outstanding. Pending
  • Rental turbines (or owned aero if that path is chosen) for first fire. Rental is weeks. Owned is 12–24+ months. That is the first-power bridge, not the campus fleet. Selected
  • Padmount transformers and PCUs (40 weeks). None in stock. Fleet size is in the equipment list. Order in P0. Calculated
  • Fiber laterals. Not on the electrical critical path, but on the tenant-ready path. Plan
  • ERCOT interconnection. Not on the Phase 1 path. Parallel 2030 branch. Record

None of the padmounts or PCUs are in stock. 160 padmounts and 372 PCUs to order at 40 weeks. Large power transformers as a class run about 128 weeks (Wood Mackenzie Q2 2025). This design does not buy a 345 kV GSU until Phase 3.

5.3Time-to-power as a distribution

First 100 MW of IT rides the standard permit, the Palo Duro lateral, rental turbines, first-tranche gear and halls. The campus adds the PSD/Title V major-source review, the second lateral, the full long-lead order, and all 3 halls. The grid path is a parallel triangular, not the campus driver.

23.5BTM IT P50, months
28BTM IT P90
20BTM IT P10
43Grid P50
05001,0002040609.15: 011.5: 013.85: 016.15: 918.5: 30120.85: 96823.15: 1,14025.5: 89027.85: 43230.15: 19332.5: 6234.85: 519.4: 022.25: 025.1: 027.9: 030.75: 033.6: 1036.4: 12439.25: 48142.1: 82644.9: 87147.75: 72850.6: 96026: 030: 4834: 36138: 76742: 1,09546: 83450: 55754: 29758: 4162: 0Months from option dayCountFirst 100 MW IT (P50 23.5 mo)Full campus (P50 45.4 mo)Grid path (P50 43 mo)
First fire P50 17.2 / P90 20.6 months. The IT-live tail is halls catching a late gas path, not a transformer surprise, unless orders slip.

What drives the tail: Palo Duro agreement stretching to nine months, TCEQ standard permit at the slow end (seven months), halls at twenty months from a month-6 start. Fiber can finish after IT live; tenants will not like that. Grid P90 is 51.3 months, a 2030 problem.

Schedule modelTriangular inputs are expert bands from due diligence, not fitted distributions. Ranking of paths is the result we will defend; the decimal is not.

5.4The bridging strategy

Behind-the-meter rental turbines, once the permit and the lateral exist, fire in weeks. Owned aero is 12–24+ months. That difference is the bridge. Model pull-forward versus waiting on ERCOT: 19.5 months at P50 (4323.5).

Convert to owned in Phase 2 when the queue and the offtake justify it. Stopping at 100 MW is Alternative B, and it leaves 250 MW of the gate unbuilt.

Behind-the-meter generation

Behind the meter buys first power. First IT lands 19.5 months ahead of the grid path. The full campus still finishes within a few months of a grid date because construction and long-lead equipment set that date, not the interconnection queue.

Islanding starts revenue earlier and hedges a queue position nobody controls. It does not pull the full campus in sooner than a grid path would.

Long-lead equipment sets the date in 35.3% of draws and the transformer and switchgear market is the reason. Ordering slots is a day-one action, ahead of FID and ahead of the air permit.

Activities that set the campus date

Share of draws in which each activity set the campus date. The schedule is only as good as its longest pole, and naming it is the point of running the model.

fit-out after first powerPSD/Title V air permitsecond gas lateral and com…long-lead equipmenthall construction020406080100fit-out after first power: 0.1PSD/Title V air permit: 2.9second gas lateral and compression: 8long-lead equipment: 35.3hall construction: 53.8Share of outcomes it gates, %
Figure 5.3. Which activity gates first power, across the schedule outcomes.
ActivityShare of outcomes it gates
hall construction53.8%
long-lead equipment35.3%
second gas lateral and compression8%
PSD/Title V air permit2.9%
fit-out after first power0.1%

The PSD and Title V review runs 21.5 months at P50 and 28.3 at P90, and it is mandatory rather than optional at this emissions rate. It nonetheless gates only 2.9% of draws, because transformer and switchgear delivery at 28 months P50 and hall construction both run longer. Permitting is the risk people expect; procurement is the one that shows up.

Why the P90 moved outConstruction durations share one execution factor per draw rather than being sampled independently. Independent sampling cancels risk that does not cancel on a real site and produces a P90 too close to the P50 to be worth quoting.

5.5Permitting summary

Phase 0 study catalog: 30 studies, $1.6–3.7M Nine months; the first eight studies start immediately. Lead times below are placeholders until agency-sourced distributions replace them.

PermitAgencyLeadStatus
CWA §404 NWP 14/51/57 or individual PendingUSACE SWT (Red) / SWF (Brazos)PCN 45–60 d; individual 6–18 monot started
ESA §7 / §10 PendingUSFWS30–135 d formalIPaC not run
Air standard permit (Phase 1) PlanTCEQweeks–months (Abilene-class)file by month 3
Air NSR (Phase 2 fleet) PlanTCEQ6–12 mofile early P1
TPDES CGP TXR150000 PlanTCEQNOI on filingSWPPP before work
Gateway GCD well permit PendingGateway GCDdistrict cycleafter pump tests
Surface water right (if any diversion) PlanTCEQTCEQ cyclenot triggered unless a surface take is added
RRC T-4 lateral PlanRRCmonthsTexas: no pre-construction delay claimed
FERC firm transport PendingFERCcommercialcapacity MUST-ASK; tariff unfiled
ERCOT large-load (Phase 3) RecordERCOT / PUCT / WETTstudy cycle; ≥$100k feefile at reopen
FAA Part 77 PendingFAA45+ dif >200 ft
DoD siting PendingDoD Clearinghouse30–90 dSheppard/Dyess
TxDOT driveway PlanChildress Districtdistrict reviewCR-117
TxDMV superload PendingTxDMVper moveroute survey MUST-ASK
Plat (separate for campus / gen / later solar) RecordKing County Commissioners Courtcommissioners courtno county building code
Antiquities / NHPA §106 PendingTHC / ACHPsurvey-dependentarchaeologist
TPDES / TLAP discharge PendingTCEQmonthsafter water chemistry
Private use network / GINR PlanERCOTmonths to yearsnot this island; Phase 3 if export