6. Risk

Each item has an owner and a close-out. The five that still block FID are in §1.4.

6.1Risk register

IDRiskPImpactMitigationOwner
R1Palo Duro fully subscribed / too small for campusHighCaps BTM first power; campus needs a second lateralCapacity ask day one; CNG/LNG as schedule bridge; do not size first power above what the letter supports; P2 gas is a separate FID.Owner / midstream
R2Queue freeze hardens past 2030HighGrid upside slips; BTM path unaffectedPhase 1 is islanded. Do not underwrite utility MW before a study window exists.Counsel
R3Blaine wells fail yield/TDSMedImport water or stay strictly dry (already BOD)Test wells first; dry plant; MAG 49 AF/yr is not an evaporative budget.Hydrogeo
R4Gypsum karst under hallsMedRelocate halls inside Ω_buildBuilding-area SSURGO shows zero gypsum in mapped horizons, but bore anyway. Avoid DQG breaks already excluded.Geotech
R5No carrier appetite for lateralsMedSite is fiber-stranded; kills tenantIRU conversations before tenant LOI. Two diverse laterals or do not claim dual-path.Fiber
R6Posted bridge on US-83 / US-82MedDetour or structure replace on LPT pathTxDMV route survey. Super-2 completes late 2028, before a 2029–31 heavy-haul window.Logistics
R7Mineral SUA refusedMedAccommodation doctrine; delay closeRunsheet + SUAs pre-LOI. Live permit API 42-269-32650 is in the block.Landman
R8LPC relisted during status reviewLow/MedSeasonal windows, possible HCPIPaC with drawn footprint before filing. Carry as Class-B scenario, not a clearance.USFWS counsel
R9Collector sections have no closed ties (architecture)KnownLosing one section drops about 33% of IT; not campus-black, not Tier III3 independent 34.5 kV islands are how 350 MW stays in catalog switchgear. Closed ties/ring before any Tier language in an SLA.Electrical
R10Padmount 40-week vs LPT 128-week classMedIT live slips if xfmr/PCU not orderedThis design uses 3.75 MVA padmounts, not 345 kV GSUs, until Phase 3. Approved alternates. Order in P0.Procurement
R11800 VDC product / code gapHigh if selectedCannot seal; insurer pushback415Y/240 is the hard gate this phase. 800 VDC is Alternative D, not the basis.Electrical
R12No FEMA flood map (Zone D)CertainInsurer and lender will not take desktop hydrologySite-specific 2D H&H is a day-one workstream. Atlas 14 100-yr 24-h is 7.79 in at the centroid.Civil
R13Expansive soils / corrosionMedFoundation and grounding redesignCarey/St. Paul LE 3.4–4.5%. IEEE 81 resistivity before C26 ground grid.Geotech / electrical PE
R14Cultural resources via Antiquities / §106UnknownSurvey delay if MMD/TIRZ or 404 nexusTHC Atlas is restricted. Commission the survey.Archaeologist
R15Large-load security if a grid path is filedHigh on grid path~$100k/MW at risk under proposed 25.194Campus does not file until Phase 3. A 350 MW filing is about $35M posted. BTM is the hedge.Finance / counsel

6.2Regulatory volatility

  • Queue freeze hardens past 2030. Phase 1 is islanded. Do not underwrite utility MW before a study window exists.
  • Mineral SUA refused. Runsheet + SUAs pre-LOI. Live permit API 42-269-32650 is in the block.
  • LPC relisted during status review. IPaC with drawn footprint before filing. Carry as Class-B scenario, not a clearance.
  • Cultural resources via Antiquities / §106. THC Atlas is restricted. Commission the survey.
  • Large-load security if a grid path is filed. Campus does not file until Phase 3. A 350 MW filing is about $35M posted. BTM is the hedge.

Large-load rules (SB6, Abbott audit, proposed 25.194) are a scenario, not a constant. Behind-the-meter generation was not paused. Species status is a live review, not a clearance. Water jurisdiction for brackish-industrial inside Gateway GCD is an open legal question. JETI eligibility splits by plat: gas and campus may qualify; solar/storage will not.

6.3Supply chain

Padmounts run 8–26 weeks standard and 40+ custom. This design uses 40 weeks as the commercial default, 160 units, none in stock. PCUs 372 units, 40 weeks, none in stock. Aero packages: weeks if rented, 12–24+ months if owned, 3–7 years if someone insists on heavy-frame. The site derate makes this worse rather than better, because the fleet is 16 machines. BESS packs are the short item. Approved-alternates (or-equal) on transformers and PCUs are how the 40-week number stays 40 weeks.

Long-leadLeadQuantityOr-equal
Padmount 34.5 kV / 415 V40 weeks in this design (8–26 standard / 40+ custom)160yes
PCU / 1,250 kW 415 V40 weeks372yes
Aero-equivalent turbines (owned)12–24+ months21 × 34.5 MW campus; 6 × first poweryes
Rental aero bridgeWeeks after permit + gasFirst-power onlyyes
BESS GFM6–12 months140 MW / 75 MWh campusyes
Fiber laterals12–24 months ROW + buildChildress + Lubbockno
345 kV GSU / yard (Phase 3)~128 weeks LPT classNot purchased this campusyes
Padmount 34.5 kV / 4…PCU / 1,250 kW 415 VPadmount 34.5 kV / 415 V: 160PCU / 1,250 kW 415 V: 372Units to order
Figure 6.1. Padmounts and PCUs to order. Log scale. Nothing is in stock.

6.4Technical

800 VDC is Alternative D, not the basis. Ring topologies are deferred.3 collector sections keep first-cycle duty at 26.5 kA, inside 63 kA catalog switchgear; they are not closed ties. Islanded dynamics (machine decrement, inverter control-law faults, transient stability) are outside this study and must be a procured study before relay settings or turbine purchase.

6.5Site

  • Blaine wells fail yield/TDS. Import water or stay strictly dry (already BOD). Test wells first; dry plant; MAG 49 AF/yr is not an evaporative budget.
  • Gypsum karst under halls. Relocate halls inside Ω_build. Building-area SSURGO shows zero gypsum in mapped horizons, but bore anyway. Avoid DQG breaks already excluded.
  • Posted bridge on US-83 / US-82. Detour or structure replace on LPT path. TxDMV route survey. Super-2 completes late 2028, before a 2029–31 heavy-haul window.
  • No FEMA flood map (Zone D). Insurer and lender will not take desktop hydrology. Site-specific 2D H&H is a day-one workstream. Atlas 14 100-yr 24-h is 7.79 in at the centroid.
  • Expansive soils / corrosion. Foundation and grounding redesign. Carey/St. Paul LE 3.4–4.5%. IEEE 81 resistivity before C26 ground grid.

Atlas 14 100-yr 24-h is 7.79 in at the centroid. That does not replace 2D H&H on a surveyed surface. Cultural resources are unknown until THC/archaeology returns.

6.6What a licensed engineer will and will not sign today

Will sign, on their own work

  • A sealed short-circuit and coordination study on a will-serve fault (or an island study with machine decrement and inverter control-law faults), not this compiler printout.
  • Structural calculations on ASCE Hazard Tool values pulled at the centroid, with geotech.
  • H&H 2D and a drainage report after Atlas 14 is applied to a surveyed surface.
  • An air-permit application package with actual engine/turbine vendor data.
  • A plat and an ALTA once the survey exists.

Will not sign

  • This document. It is a Class 4 drafting aid and a single-run estimate.
  • Uptime Institute Tier III (or IV) while collector sections have no closed ties.
  • A contractual PUE or WUE until wells, weather file, and a tenant rack schedule exist.
  • IEEE 80 touch/step without site resistivity (IEEE 81).
  • A 345 kV interconnection design without WETT fault duty and service MVA.
  • 800 VDC distribution as a code-compliant basis of design in this phase.
Not a sealed setThis site is a Class 4 study. It is not a sealed construction set.

Division of responsibility

PartyOwns
OwnerLand close, Palo Duro capacity, fiber IRUs, offtake, incentives, air-permit applicant, PE hire
EPC / national DC builderPad, halls, MV/LV, dry plant, commissioning Levels 1–5, HSE, as-builts/COBie
Midstream EPC9.5 mi first lateral; P2 second feed and compression
Generation OEM / packagerRental bridge then owned aero-equivalent + recip halls; BESS GFM / NFPA 855
TSP / ERCOT (Phase 3)345 kV cut-in, large-load study, metering. Not on the first-power path.
Co-op (construction power)Will-serve for construction only. South Plains EC or Tri-County EC; parcel-level confirmation is still outstanding.
Licensed PEsSealed S/C, coordination, arc-flash, H&H, structural, air package, ground grid (C26)
This toolClass 4 drafting aid. run_id is an audit stamp, not a seal.